Higginsville Bridge

This project consisted of getting 250 foot girders from one side of the river to the other. Our towers were used to support the single span beams by utilizing a barge. The girders were extended 80 foot past the barge resting on a combination of our static and Hydraulic towers. The barge was pulled the rest of the way across the river by two excavators until the girders were precisely docked in place on the other side