Pennsylvania Turnpike NB-129 Bridge Replacement

BDB Bridge supplied the Pennsylvania Turnpike Commission NB-129 Bridge Replacement (Contract A020.00T002-3-03). This new bridge carries Morris Road over the Northeast Extension.

​

This project required J.F. Shea Construction to erect 4 continuous girder lines with one center pier. Each girder line consisted of 3 girder segments (2 field splices).

​

The Turnpike Commission had planned for multiple night time traffic stoppages over the course of several nights. We proposed supporting the western segment on our Hydra-Tower System with a single right lane closure. The remaining segments would be erected from the opposite side of the road with a single crane with only one detour. This was far less inconvenient for the traveling public.